PRINCE2-Foundation Free Exam Study Guide! (Updated 340 Questions) PRINCE2-Foundation Dumps for PRINCE2 Certification Certified Exam Questions and Answer NEW QUESTION 162 Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change? A. Directing a project B. Managing a stage boundary C. Controlling a stage D. Starting up a project Answer: C Explanation:Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-prince2 [...]

PRINCE2-Foundation Free Exam Study Guide! (Updated 340 Questions) [Q162-Q187]

Share

PRINCE2-Foundation Free Exam Study Guide! (Updated 340 Questions)

PRINCE2-Foundation Dumps for PRINCE2 Certification Certified Exam Questions and Answer

NEW QUESTION 162
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  • A. Directing a project
  • B. Managing a stage boundary
  • C. Controlling a stage
  • D. Starting up a project

Answer: C

Explanation:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-prince2

 

NEW QUESTION 163
Which does a Project Manager produce to define and control the work to be done?

  • A. Work Package
  • B. Team Plan
  • C. Stage scope tolerance
  • D. Configuration Item Record

Answer: A

 

NEW QUESTION 164
Which does NOT reflect the PRINCE2 principle of continued business justification?

  • A. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
  • B. The business justification drives decision making
  • C. There must be a justifiable reason for starting a project
  • D. If a project can no longer be justified, it should be stopped

Answer: A

 

NEW QUESTION 165
Which risk response is applied on a pain/gain basis?

  • A. Exploit
  • B. Enhance
  • C. Accept
  • D. Share

Answer: D

Explanation:
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-2017-risk-responses-and-planning/

 

NEW QUESTION 166
Which is one of the six aspects of project performance to be managed?

  • A. Efficiency
  • B. Timescales
  • C. Work
  • D. Estimate

Answer: B

Explanation:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/
Introduction:_The_PRINCE2_Foundation_Training_Manual#Six_variables_.2F_six_performance_targets

 

NEW QUESTION 167
Which role is part of the project management team?

  • A. Change Authority
  • B. Corporate or programme management
  • C. Quality assurance
  • D. Stakeholder

Answer: A

 

NEW QUESTION 168
Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  • A. Managing Product Delivery
  • B. Controlling a Stage
  • C. Closing a Project
  • D. Managing a Stage Boundary

Answer: C

Explanation:
Section: Volume A
Explanation

 

NEW QUESTION 169
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

  • A. Both 1 and 2 are true
  • B. Only 1 is true
  • C. Neither 1 or 2 are true
  • D. Only 2 is true

Answer: C

 

NEW QUESTION 170
Where should the names of those who are to approve a product be recorded?

  • A. Checkpoint Report
  • B. Product Description
  • C. Product Status Account
  • D. Configuration Item Record

Answer: B

 

NEW QUESTION 171
Which is a purpose of a Lessons Log?

  • A. Note any lessons that are raised in Checkpoint Reports
  • B. Raise improvements with Project Assurance
  • C. Escalate lessons to the Project Board
  • D. Record that corrective action is being taken

Answer: A

 

NEW QUESTION 172
To meet the minimum requirements for applying the progress theme, what must be considered?

  • A. How lessons will be learned
  • B. Who is responsible for reporting on progress
  • C. Which management products will be baselined
  • D. How time-driven reports will be produced

Answer: D

Explanation:
Reference http://prince2.wiki/Themes

 

NEW QUESTION 173
What is a purpose of a Benefits Review Plan?

  • A. Provide details of the time and effort needed to carry out the planned benefits reviews
  • B. Document the justification for undertaking the project, based on the estimated costs versus the anticipated benefits
  • C. Give a detailed analysis of only those benefits that were realized before the project closed
  • D. Provide information regarding unfinished work to the group which will support the project's products in their operational life

Answer: A

 

NEW QUESTION 174
What is the definition of a project outcome?

  • A. The result of the change derived from using the project's outputs
  • B. The project's specialist products.
  • C. The reason for the project
  • D. A measurable improvement that is perceived as an advantage by one or more stakeholders

Answer: A

 

NEW QUESTION 175
Which is a purpose of the Initiating a Project process?

  • A. Decide if it is worthwhile to initiate a project
  • B. Decide on the project approach
  • C. Identify the number of Work Packages required
  • D. Establish solid foundations for a project

Answer: D

 

NEW QUESTION 176
Which is a purpose of the Directing a Project process?

  • A. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
  • B. Establish the level of control required by the Project Board after initiation.
  • C. Provide the information required to confirm if it is worthwhile to initiate a project
  • D. Enable overall control of a project to be exercised by the Project Board

Answer: D

 

NEW QUESTION 177
Which risk response type is appropriate to respond to an opportunity?

  • A. Exploit
  • B. Accept
  • C. Transfer
  • D. Fallback

Answer: A

 

NEW QUESTION 178
Who carries out audits that are independent of the project?

  • A. Project Assurance
  • B. Project Manager
  • C. Quality assurance
  • D. Project Support

Answer: C

 

NEW QUESTION 179
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

  • A. Project mandate
  • B. Project Initiation Documentation
  • C. Benefits Review Plan
  • D. Project Brief

Answer: B

 

NEW QUESTION 180
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity.

  • A. Avoid
  • B. Transfer
  • C. Reduce
  • D. Share

Answer: D

 

NEW QUESTION 181
What is a supplier of a PRINCE2 project responsible for?

  • A. Providing resources to deliver the project outputs
  • B. Establishing the project's governance
  • C. Providing the project mandate
  • D. Realizing the benefits from the project

Answer: A

Explanation:
Explanation
Reference http://prince2.wikidot.com/senior-supplier

 

NEW QUESTION 182
Which is a benefit of using PRINCE2?

  • A. Includes many of the proven planning techniques, such as critical path analysis
  • B. Is a method specifically designed for technical projects
  • C. Can be used to manage both projects and programmes
  • D. Provides for the efficient and economic use of management time

Answer: D

 

NEW QUESTION 183
Which management product is used to record relationships between specialist products?

  • A. Product status account
  • B. Issue register
  • C. Change control approach
  • D. Configuration item record

Answer: D

 

NEW QUESTION 184
Which is a purpose of the Starting up a Project process?

  • A. Define the project controls
  • B. Record any identified risks in the Risk Register
  • C. Define the means of communication between the project and corporate or programme management
  • D. Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate

Answer: D

 

NEW QUESTION 185
Which is an objective of the quality review technique?

  • A. To define the quality methods required within a project
  • B. To baseline a product
  • C. To determine the quality responsibilities of a project team
  • D. To provide a common understanding of what products a project will create

Answer: B

 

NEW QUESTION 186
Where should an off-specification be recorded?

  • A. Work Package
  • B. Risk Register
  • C. Configuration Management Strategy
  • D. Issue Register

Answer: D

 